insights

A Cross-Canada Collaboration Helps to Protect a National Historic Site and restore the Lake Ontario shoreline

Niagara-on-the-Lake is a bustling, picturesque town located on the shores of Lake Ontario, at the mouth of the Niagara River. Known for its wineries and summer theatre, the town also attracts visitors to the Fort Mississauga National Historic Site, a large, square brick defensive tower set along the Niagara River shoreline. 

 

 

 

In recent years, severe climate events have significantly eroded portions of the lake’s shoreline especially along a roughly 400m-long strip of land by the Fort. This portion of shoreline, located by a nearby golf course, had up to five metres disappear causing the slope to destabilize and potentially threaten the integrity of adjacent infrastructures and natural habitats.  

 

 

 

Parks Canada, the federal department which manages the Fort, wanted to build a sustainable, cost-effective solution to this erosion problem. Given the lengthy, strong relationship between the Agency and Englobe, the company got the nod to assemble a team of experts from offices across the country to develop a long-term solution.    

A project with deep cultural and historic importance 

 

 

 

Although a portion of the eroded shoreline had been reinforced in 2018, PCA was anxious to protect its remaining historic assets from further deterioration. The Fort Mississauga National Historic Site attracts thousands of visitors every year and is an important example of military construction. 

 

 

 

Completed after the War of 1812, the Fort and its central tower were strategically positioned to protect the British/Canadian side of the border and served as a counterpoise to Fort Niagara on the American side. It’s also unique, as it is the only remaining example of this type of fortification - a square tower within star-shaped earthworks – in Canada.  

Unique challenges to reinforce slope stability  

 

 

 

For this project, the team was tasked with providing tender-ready documents, drawings and specifications, along with engineering services during the tender and construction phases. The team would also offer monitoring and inspection services throughout the construction phase of the shoreline revetment it had designed. 

 

 

 

The project’s complexity created unique challenges for the team. 

Environmental considerations were an important aspect, so the construction work was carried out during a short window in wintertime to minimize disturbance to local fish habitats. Another element was preserving the site’s archeological heritage, which meant we had to protect the Fort from damage throughout construction. Finally, there was the location itself, with the lake on one side and the Fort on the other, so we had to ensure we weren’t impacting either one.

Project Manager Kyle McConnell, P Eng., notes.
A cross-country, multi-disciplinary collaborative effort 

 

 

 

Gathering the necessary expertise for this project was also a complex task, resulting in a true cross-Canada effort

  1. Preliminary analyses completed by Kyle McConnell and the Atlantic team examined the impacts of snow, wind, ice and other conditions on the shoreline.  
  2. Next, Director of Operations Brennan Bailey and his team from Southern Ontario conducted a topographical survey to identify soil conditions and characteristics. 
  3. Then came a geotechnical investigation, handled by Guillaume Joyal, Director of Operations in Quebec, and his team. 
  4. Lastly, Project Engineer Tim Guan led a team of water works experts from MPE, Englobe’s Western subsidiary, who examined all collected data from a hydrology perspective and made recommendations for the shoreline revetment’s design and construction.  

 

 

 

Kyle was especially impressed at the collaborative spirit shown by everyone on the project team. 

We were able to get this project done efficiently and on time to meet the client’s expectations, which doesn’t happen as easily in these larger-scale projects as it would if everyone was sitting next to each other in the same office. “It shows the value of being effective communicators and setting reasonable expectations. I'm most proud of being able to work together on these types of projects with colleagues from different offices and regions across Canada – literally.

Project Manager Kyle McConnell, P Eng., notes.
Monitoring progress 

 

 

 

Curtis Mossman, who worked in Englobe’s Kitchener office at the time, was one of two inspectors responsible for providing administrative support and inspection services during the construction phase, which was awarded to an experienced local contractor. 

This was my first time working on a project with this much ground coverage, so to speak, and I was nervous. Thankfully, everyone was extremely helpful, and I received a lot of guidance and mentoring along the way. It was a very good collaborative effort.

says Curtis Mossman, Technician, Instrumentation, at Englobe Corp.

The project was substantially completed in spring 2024. Today, this area is protected against a 1-in-100-year climate event, thus preserving the integrity of an important Canadian National Historic Site. Additionally, a new access path created at the top of the protective revetment, originally intended for maintenance purposes, can also be used by pedestrians wishing to enjoy stunning views of Lake Ontario and the Fort.  

 

 

 

This project was an outstanding example of the Englobe’s team collaborative spirit and united expertise. These qualities combined to create a sustainable, robust design that will preserve the Lake Ontario shoreline from further erosion and enthrall visitors to Fort Mississauga for decades to come.    

Englobe is recognized as Canada’s leader in the fields of environmental management, engineering, and asset integrity and quality management.

Dare to make a positive impact

See career opportunities